Selected work

Projects where coordination becomes practical

Real design and engineering scope, visible through systems, models, documentation, and resolved interfaces across complex buildings and infrastructure

  • 24 selected projects
  • 6 sectors
  • Europe delivery context
Brownfield Industrial Extension: 20,000 m² Inside an Operating Facility — project by TEBIN
Industrial & ManufacturingEurope

Brownfield Industrial Extension: 20,000 m² Inside an Operating Facility

How TEBIN coordinated a 20,000 m² extension within a 245,000 m² European production facility using 8 BIM models, 800+ drawings, and one digital workflow.

  • 20,000 m²Extension area
  • 8Coordinated discipline models
  • 800+Design drawings
View project
Berlin Residential Heating Case: TEBIN's BIM and LINEAR Workflow — project by TEBIN
ResidentialBerlin, Germany

Berlin Residential Heating Case: TEBIN's BIM and LINEAR Workflow

How TEBIN designed two Berlin residential buildings with 4,200 m² of conditioned space and 24,000 m of piping in a BIM and LINEAR workflow.

  • 4,200+ m²Conditioned floor area
  • 24,000 mEmbedded heating pipework
  • 2Multifamily buildings
View project
7,000 m² Industrial Plant in Central Europe: Full-Scope BIM Delivery — project by TEBIN
Industrial & ManufacturingCentral Europe

7,000 m² Industrial Plant in Central Europe: Full-Scope BIM Delivery

A 7,000 m² production facility delivered across architecture, structural, civil, MEP, and fire protection in one coordinated BIM model.

  • 7,000 m²Production facility
  • 6Coordinated disciplines
  • 1Federated delivery environment
View project
Fuel Backup System Design: From Technical Input to Buildable Documentation — project by TEBIN
Mission-Critical InfrastructureEurope

Fuel Backup System Design: From Technical Input to Buildable Documentation

How TEBIN transformed fuel-system technical inputs into coordinated BIM models, schematics, supports, trench drawings, and construction documentation.

  • 1:1Equipment geometry scale
  • LODSet for construction review
  • BIMCoordinated system package
View project
TEBIN Standard 10,000 m² Dry Warehouse: BIM-Based Reference Design for Engineering Partners — project by TEBIN
Logistics & DistributionEuropean reference design

TEBIN Standard 10,000 m² Dry Warehouse: BIM-Based Reference Design for Engineering Partners

TEBIN's BIM-based standard design for a 10,000 m² dry warehouse that engineering companies can reuse as a coordinated digital foundation.

  • 10,000 m²Reference warehouse
  • 12 × 24 mStructural grid
  • 12 mStorage height basis
View project
Replacing the UPS Systems of a Data Centre That Could Not Be Switched Off — project by TEBIN
Data CentersEurope

Replacing the UPS Systems of a Data Centre That Could Not Be Switched Off

Design for replacing the uninterruptible power supply systems and battery banks of a data centre in continuous operation: replacement strategy, removal sequencing, and updated electrical calculations, protection settings, and as-built documentation.

  • LP1–LP4HOAI design stages
  • LiveFacility in operation throughout
  • As-builtDocumentation reconciled
View project
The Substation Behind the Data Centres: Over 200 MW at 150/20/10 kV — project by TEBIN
Data CentersThe Netherlands

The Substation Behind the Data Centres: Over 200 MW at 150/20/10 kV

Civil and electrical basic design for a grid substation of over 200 MW at 150/20/10 kV, serving a data centre cluster in the Netherlands: the power infrastructure that sits upstream of the halls.

  • 200+ MWSubstation capacity
  • 150/20/10 kVVoltage levels
  • 2Disciplines: civil and electrical
View project
From Printing Works to Data Centre: Electrical, BMS, and Fire Safety Design for a Conversion — project by TEBIN
Data CentersGermany

From Printing Works to Data Centre: Electrical, BMS, and Fire Safety Design for a Conversion

Concept and basic design of electrical, building management, and fire safety systems for the conversion of an existing printing facility into a data centre of under 10 MW, with approximately 9,000 m² of white space.

  • Under 10 MWIT power
  • ~9,000 m²White space
  • ConversionExisting building reused
View project
Testing a Data Centre That Is Already Full: Permanent Load Bank Design — project by TEBIN
Data CentersGermany

Testing a Data Centre That Is Already Full: Permanent Load Bank Design

A permanent load bank strategy for a data centre in full operation: testing concept, integration across redundant electrical paths, load bank locations, busbar routing, and updated single-line diagrams.

  • LP1–LP4HOAI design stages
  • LiveFacility in operation
  • PermanentTesting capability built in
View project
Detailed Design Across an EV Manufacturing Campus of Over 250,000 m² — project by TEBIN
EV ManufacturingGermany

Detailed Design Across an EV Manufacturing Campus of Over 250,000 m²

Detailed design and as-built documentation across the production buildings of an EV manufacturing campus in Germany: cell production, laboratories, stamping, and general assembly, with a combined footprint over 250,000 m².

  • 250,000+ m²Combined building footprint
  • 4+Production building types
  • 5DBIM standards developed
View project
Building Services for a Biosafety Level 3 Laboratory: 16,800 m² Under Containment Rules — project by TEBIN
Laboratories & Life SciencesGermany

Building Services for a Biosafety Level 3 Laboratory: 16,800 m² Under Containment Rules

MEP design for a six-storey, 16,800 m² laboratory building classified Biosafety Level 3: HVAC, water, sewerage, sprinklers, laboratory gases, electrical, fire detection, and security, designed to biosafety requirements.

  • BSL-3Biosafety containment level
  • 16,800 m²Laboratory building area
  • 60 / 40Laboratory to office ratio
View project
Emergency Power Fuel Infrastructure for a Data Centre: 16-Tank Storage and Distribution Design — project by TEBIN
Mission-Critical InfrastructureThe Netherlands

Emergency Power Fuel Infrastructure for a Data Centre: 16-Tank Storage and Distribution Design

Design of fuel storage and distribution for a data centre emergency power system: 16 diesel tanks, 8 pump rooms, 4 filling cabinets, and documentation to As-Built.

  • 16Diesel fuel tanks
  • 8Pump rooms
  • 4Filling cabinets
View project
Fuel and Urea Systems for a Multi-Level Data Centre: LOD 450 Detailed Design — project by TEBIN
Mission-Critical InfrastructureGermany

Fuel and Urea Systems for a Multi-Level Data Centre: LOD 450 Detailed Design

LOD 450 design of fuel and urea systems for a data centre with vertically stacked generators: 3 × 100 m³ fuel tanks, 4 × 10 m³ DEF tanks, and combined pump rooms.

  • 3 × 100 m³Fuel storage tanks
  • 4 × 10 m³Urea (DEF) tanks
  • LOD 450Detailed design standard
View project
Data Centre Expansion Zone: Underground Fuel Storage and Cross-Zone Urea Tie-In — project by TEBIN
Mission-Critical InfrastructureGermany

Data Centre Expansion Zone: Underground Fuel Storage and Cross-Zone Urea Tie-In

LOD 450 design for a data centre expansion zone: 5 × 100 m³ underground fuel tanks, 3 × 10 m³ indoor DEF tanks, and a cross-zone urea tie-in serving 4 generators.

  • 5 × 100 m³Underground fuel tanks
  • 3 × 10 m³Indoor urea (DEF) tanks
  • 4Generators served via tie-in
View project
Urea (DEF) Distribution for a Data Centre: One Storage Tank, 22 Generator Sets — project by TEBIN
Mission-Critical InfrastructureGermany

Urea (DEF) Distribution for a Data Centre: One Storage Tank, 22 Generator Sets

Execution design of a urea (DEF) system for a data centre: a 50 m³ storage tank with tanker offload and a modular pump skid distributing to 22 generator sets.

  • 50 m³Urea storage tank
  • 22Generator sets supplied
  • 2Independent filling points
View project
Modular Aviation Fuelling Station: Full Design from Concept to As-Built — project by TEBIN
Aviation Fuel InfrastructureGermany

Modular Aviation Fuelling Station: Full Design from Concept to As-Built

Full design of a modular aviation fuelling station in Germany: station concept, container fit-out, and the fuel path from storage tank to aircraft — LPH 1 to 5.

  • LPH 1–5HOAI design stages delivered
  • 1Modular container station
  • As-BuiltFinal documentation stage
View project
Food Retail Distribution and Production Hub: Integrated Design for a 200,000 m² Complex — project by TEBIN
Logistics & Food RetailCentral Europe

Food Retail Distribution and Production Hub: Integrated Design for a 200,000 m² Complex

Integrated design and engineering for a 200,000 m² food retail hub combining ambient warehouses, chilled and frozen storage, and production areas.

  • 200,000 m²Total complex scale
  • 40,000 m²Chilled and frozen storage
  • 16,000 m²Production area
View project
Construction Equipment Rental Service Centre: Design for Maintenance, Washing, Repair, and Fleet Operations — project by TEBIN
Industrial Service & Equipment RentalEastern Europe

Construction Equipment Rental Service Centre: Design for Maintenance, Washing, Repair, and Fleet Operations

Full multidisciplinary design for an equipment rental service centre with wash bay, repair workshops, paint booth, spare-parts storage, and site utilities.

  • ~7,000 m²Main facility scale
  • 3Office levels
  • Full designConcept to working documentation
View project
Dry Building Mixes Production Plant: Full Basic Design for an Industrial Facility — project by TEBIN
Industrial & ManufacturingUkraine

Dry Building Mixes Production Plant: Full Basic Design for an Industrial Facility

Full Basic Design for a dry building mixes production plant with a 50.4 m silo body, 17,284.5 m² listed building area, and a process-driven industrial design logic.

  • 50.4 mSilo body height
  • 17,284.5 m²Listed building area
  • 6.31 haDesign boundary site
View project
Reconstruction of a Logistics Warehouse Complex: Full Project Design — project by TEBIN
Logistics & DistributionUkraine

Reconstruction of a Logistics Warehouse Complex: Full Project Design

Full Project Design for reconstructing a damaged operating warehouse complex with 46 loading docks, more than 54,000 m² of area, and a civil protection shelter.

  • 54,000+ m²Area after reconstruction
  • 46Loading docks
  • 300Civil protection shelter capacity
View project
Hotel and Office Centre: Vertical Mixed-Use Design — project by TEBIN
Hospitality & CommercialUkraine

Hotel and Office Centre: Vertical Mixed-Use Design

Architectural design correction for a hotel and office centre on a compact 0.31 ha urban site, coordinating hotel, office, parking, technical, and fire-safety logic.

  • 0.31 haCompact urban site
  • 47,000+ m²Overall building area
  • 546Apartment-type hotel rooms
View project
85,000 m² Commercial Complex: Integrated Multidisciplinary Design — project by TEBIN
CommercialKyiv, Ukraine

85,000 m² Commercial Complex: Integrated Multidisciplinary Design

Integrated design and engineering for a six-building commercial complex, connecting BIM coordination, value engineering, quantities, and authority documentation.

  • 85,000 m²Gross building area
  • 6Office buildings
  • 0.85GLA to GBL target ratio
View project
UNIT.City BIM and VDC Programme: From Design Models to Construction Use — project by TEBIN
Commercial & Mixed UseKyiv, Ukraine

UNIT.City BIM and VDC Programme: From Design Models to Construction Use

A multi-project BIM and Virtual Design and Construction programme connecting coordinated models, common data environment workflows, and construction planning.

  • 100,000+ m²Programme area
  • 40+Coordinated BIM models
  • 65Client and contractor staff trained
View project
Mining Facility BIM Coordination Across 44 Buildings — project by TEBIN
Mining & Heavy IndustryPoltava, Ukraine

Mining Facility BIM Coordination Across 44 Buildings

BIM reconstruction and coordination for a mining facility programme covering 44 buildings, 29 hectares of laser-scanned site, and about 700 source drawings.

  • 44Buildings reviewed
  • 29 haLaser-scanned site area
  • 3,000Coordination issues identified
View project