TIRE MANUFACTURING MIXING PLANT, MICHELIN

SCOPE & SOLUTIONS

Large-scale industrial project. Extension of production buildings (20 000 m2) integrated in existing brownfield facilities (total plot area is 245 000 m2). Multi-disciplinary project developed for high value process requirements.

HOW DOES IT WORK

Gathering and coordination of multi-discipline teams with domain experience
Engineering works fully BIM based as single data source
Common Data Environmental (CDE)
Flexible and transparent collaboration between project stakeholders. Including the training and education of all project members to deliver the project in respect of Agile principles within the challenging schedule and high technical requirements

RESULTS & ACHIEVEMENTS

Simple and standard workflows and project presets
Good scheduling
Comply to the all investor requirements, local regulations/norms and respect of cultural differences
Various cost ownership studies and scenarios
Delivery the high value requirements, knowledge and industrial facilities in compliance to the top-secret process technologies (tight fit with process requirements)
Created 8 multidisciplinary building models (Architectural, Structural, Civil, HVAC, Fluids, Water & Sewerage, Electrical, Fire Fighting), including federated model
BIM based engineering calculations (hydraulic, air exchange, balancing charts, pipe sizing, indoor and outdoor lighting analysis, cable sizing and load schedules, structural analysis using Robot)
Model integrated schematics
Generated over 800 drawings
Automatically generated all disciplines BoQ
Pilot 4D construction simulation as preparation stage for Virtual Design and Construction (VDC)

CLIENT:

International engineering company

ROLE:

Egineering of Basic and Tender packages

LOCATION:

Poland

COMMUNICATION:

E-mail free communication based only on MS Teams (no emails anymore)
On-line meetings, desktop sharing, on-line reviews
Quick meeting notes (there are no routine documentation)

TEAM & DURATION:

65 project members in 7 different locations (Ukraine, Poland, France)
Total duration – 5 month

TOOLS:

Autodesk Revit
Civil 3D
Robot
BIM 360
Navisworks
MagiCAD
ElumTools™
MS Teams
MS Project
Synchro
Worksection

TECHNOLOGIES:

BIM
VR
VDC
Agile
SCRUM
Kanban

AGILE:

No waterfall anymore
The first project fully implemented in SCRUM
Total duration is 10 sprints of 2 weeks each
About 200 tasks the team has covered every sprint
Team has passed its way from directed-by-manager to self-organized team